On January 31, 2024, the National Electricity Regulatory Entity (in Spanish “Ente Nacional Regulador de la Electricidad”, hereinafter “ENRE”) published Resolution 65/2024 (“Resolution 65”), introducing changes to the regulation applicable to electrical power transmission and distribution grid expansions and connection requests, with the end-goal of simplifying each of the below processes.

To that end, Resolution 65:

  1. Eases the process for approving minor scale electrical power transmission or distribution grid expansion works.
  2. Approves a new methodology to assess requests aimed at constructing or expanding electrical power transmission or distribution grid expansions, other than those set forth in (a) above.
  3. Approves a new methodology to assess connection applications to the existing electrical power grid; and
  4. Creates two registries for expansion and connection requests to the electrical power grid.

 

For additional information, please contact Nicolás Eliaschev, Javier Constanzó, Daiana Perrone and/or Victoria Barrueco.